A Guide to the Oregon Removal-Fill Permit Requirements, Process, and Compliance
The Oregon Removal-Fill Permit is a critical component of the state's environmental regulatory framework, designed to protect its invaluable wetlands, waterways, and aquatic resources from unregulated alteration or destruction. This comprehensive guide delves into the intricacies of the permit, enabling readers to understand its legal context, navigate the application process, and manage ongoing compliance obligations. By exploring real-world examples, best practices, and recent regulatory changes, this resource equips stakeholders with the knowledge and tools necessary to successfully obtain and maintain compliance with the Oregon Removal-Fill Permit. From detailing the permit's specific requirements and exemptions to leveraging cutting-edge technology for streamlined site selection and monitoring, this guide serves as an indispensable reference for anyone seeking to develop projects in Oregon while upholding the state's commitment to environmental stewardship.
GENERAL INFORMATION
Removal-Fill Permit Key Details
Issuing Agency: The Oregon Department of State Lands (DSL) is responsible for issuing the Oregon Removal-Fill Permit.1
Year Established: The Oregon Removal-Fill Law was enacted in 1967, establishing the permit system.2
Legal References: The primary legal documents governing the permit are the Oregon Revised Statutes (ORS) 196.795-990 and Oregon Administrative Rules (OAR) 141-085.3
Date Last Amended: The most recent amendments to the Oregon Removal-Fill Permit were made in 2019.
Other Key Facts: The Oregon Removal-Fill Permit is a critical tool for protecting Oregon's wetlands, waterways, and other aquatic resources from unregulated alteration or destruction.
Oregon Removal-Fill Permit Overview
The Oregon Removal-Fill Permit operates within the state's comprehensive environmental regulatory framework, which aims to balance economic development with the protection of Oregon's natural resources. The permit primarily addresses concerns related to the alteration or destruction of wetlands, waterways, and other aquatic habitats due to dredging, filling, or other removal activities.4
The Oregon Department of State Lands (DSL) is the primary agency responsible for administering the permit, with support from other state agencies such as the Oregon Department of Environmental Quality (DEQ) and the Oregon Department of Fish and Wildlife (ODFW).
The Oregon Removal-Fill Law was enacted in 1967 in response to growing concerns about the loss of wetlands and other aquatic habitats due to unregulated development activities. Over time, the permit has evolved to incorporate new scientific understanding and regulatory best practices, with the most recent amendments occurring in 2019.
Which Resources Are Regulated By Removal-Fill Permit?
The Oregon Removal-Fill Permit plays a crucial role in protecting the state's diverse and ecologically significant environmental resources. The permit specifically regulates activities that involve the removal, filling, or alteration of materials in wetlands, streams, rivers, estuaries, and other waters of the state.5
These protected resources include:
- Wetlands, such as marshes, swamps, and bogs
- Rivers, streams, and creeks
- Estuaries and tidal areas
- Lakes and ponds
- Other waters of the state, as defined by Oregon law6
The Oregon Removal-Fill Permit protects these resources from unregulated dredging, filling, and removal activities that could degrade water quality, harm aquatic habitats, and impact fish and wildlife populations. By requiring a permit for these activities, the state ensures that potential environmental impacts are carefully evaluated and mitigated, helping to maintain the ecological integrity of Oregon's precious aquatic resources.
Transect can help: Pinpoint environmental risks early
Reduce unforeseen delays and costs by identifying environmental risks early-on using unmatched data.
Learn MorePROJECT APPLICABILITY & REQUIREMENTS
When Oregon Removal-Fill Permits Are Required
Understanding when an Oregon Removal-Fill Permit is required is crucial for developers, environmental consultants, and other stakeholders involved in projects that may impact Oregon's waters. This permit is designed to protect the state's valuable aquatic resources and ensure that any activities involving the removal or fill of material in waters of the state are conducted in an environmentally responsible manner.
The following table outlines the types of activities, actions, or materials that trigger the need for an Oregon Removal-Fill Permit, along with the associated environmental considerations and potential impacts:
Activity/Action/Material | Environmental Considerations | Potential Impacts |
---|---|---|
Dredging | - Sediment disturbance - Turbidity - Aquatic habitat alteration | - Water quality degradation - Harm to aquatic organisms - Loss of benthic habitat |
Filling | - Wetland encroachment - Floodplain alteration - Hydrological changes | - Loss of wetland functions - Increased flood risk - Altered stream flow and habitat |
Grading | - Soil erosion - Sedimentation - Stormwater runoff | - Siltation of waterways - Degradation of aquatic habitats - Nutrient and pollutant loading |
Excavation | - Removal of riparian vegetation - Bank destabilization - Dewatering | - Loss of shade and habitat - Increased erosion potential - Temporary water quality impacts |
In-water structures | - Altered flow patterns - Fish passage obstruction - Substrate modification | - Changes in sediment transport - Fragmentation of aquatic habitats - Disruption of benthic communities |
It is important to note that the Oregon Department of State Lands (DSL) administers the Oregon Removal-Fill Law, which requires permits for projects that involve 50 cubic yards or more of removal or fill in waters of the state, including wetlands7. However, even projects below this threshold may require a permit if they are deemed to have significant environmental impacts.
Oregon Removal-Fill Permit Exemptions
While the Oregon Removal-Fill Permit is necessary for many activities involving the removal or fill of material in waters of the state, certain activities are exempt from these requirements. Understanding these exemptions is essential for project proponents to determine whether their proposed work qualifies for an exemption or if a permit is needed.
The following list details specific exemptions to the Oregon Removal-Fill Permit, including any conditions or limitations that apply:
Maintenance and Reconstruction of Existing Structures: The maintenance or reconstruction of existing structures, such as dams, dikes, levees, and transportation facilities, is exempt from permit requirements, provided that the structure remains within its original footprint and does not increase in size8.
Temporary Impacts: Temporary removal or fill activities that are completed within a specified timeframe (generally 24 months) and restore the affected area to its original condition may be exempt from permitting. This exemption is subject to approval by the DSL9.
Certain Agricultural Activities: Some agricultural activities, such as the construction of irrigation ditches, maintenance of farm ponds, and the removal of debris from drainage ditches, are exempt from permit requirements. However, these exemptions are limited in scope and may have specific conditions attached10.
Prospecting and Nonmotorized Mining: Small-scale prospecting and nonmotorized mining activities, such as panning for gold, are generally exempt from permit requirements11.
Emergency Repairs: Emergency repairs to existing structures or facilities that are necessary to prevent imminent danger to life, property, or the environment may be exempt from permit requirements. In such cases, the DSL should be notified as soon as possible, and any necessary remedial actions must be taken12.
Consultation Guidance
When determining if a project qualifies for an exemption, it is recommended to consult with the Oregon Department of State Lands (DSL) to confirm the applicability of the exemption. Project proponents should provide detailed information about the proposed activity, including its location, scope, and potential environmental impacts. The DSL can offer guidance on whether the project meets the criteria for an exemption or if a permit is required.
In some cases, the DSL may request additional information or require a site visit to assess the project's eligibility for an exemption. It is essential to engage with the DSL early in the project planning process to ensure that all necessary permitting requirements are addressed and to avoid potential delays or enforcement actions.
Transect can help: Evaluate sites faster
Decide quickly and confidently whether to advance a potential project site.
Learn MorePERMIT APPLICATION & PROCESS
Removal-Fill Permit Pre-Application Considerations & Planning
The Oregon Removal-Fill Permit process is a crucial component of any large-scale development project in the state that involves the removal or filling of material in wetlands or waterways. It is essential to consider the permit requirements early in the project lifecycle to ensure smooth integration with other project phases and milestones.
A typical project lifecycle with the Oregon Removal-Fill Permit process may follow this timeline:
- Project Conception (Month 1)
- Feasibility Studies (Months 2-4)
- Site Selection (Months 5-6)
- Preliminary Design (Months 7-9)
- Pre-Application Meeting (Month 10)
- Permit Application Preparation (Months 11-13)
- Permit Submission (Month 14)
- Agency Review (Months 15-18)
- Permit Decision (Month 19)
- Final Design & Construction (Months 20-36)
- Project Completion (Month 37)
Early engagement with the state permitting agency through pre-application meetings can help identify potential issues and guide project design to minimize environmental impacts. The permit process can significantly influence site selection, design, and construction timelines, making it crucial to factor in adequate time for permit preparation, submission, and agency review when planning the overall project schedule.
Removal-Fill Permit Application Requirements & Submission
A complete Oregon Removal-Fill Permit application requires the submission of various forms, documents, and supporting materials to demonstrate the project's compliance with state regulations and its efforts to minimize environmental impacts.
The key components of an Oregon Removal-Fill Permit application include:
Application Form: The official Oregon Department of State Lands (DSL) Joint Permit Application Form must be completed and signed by the applicant.[^200]
Project Description: A detailed narrative describing the proposed project, its purpose, location, and scope, including the amount and type of material to be removed or filled.[^201]
Site Plans and Maps
Environmental Assessment
Alternatives Analysis
Mitigation Plan
Public Notice
Application Fee
The purpose of these application components is to provide the Oregon DSL with sufficient information to evaluate the project's compliance with state regulations, assess its environmental impacts, and determine whether the permit should be granted, conditioned, or denied.
The Removal-Fill Permit Review & Decision Process
The Oregon Removal-Fill Permit process should be initiated early in the project lifecycle, ideally during the preliminary design phase, to allow sufficient time for agency review and public comment. Pre-application consultations with the Oregon Department of State Lands (DSL) are highly recommended to discuss project plans, potential impacts, and permit requirements before submitting a formal application.
The key steps in the Oregon Removal-Fill Permit review and decision process are:
Pre-Application Consultation: The applicant meets with DSL staff to discuss the project, review application requirements, and identify potential issues or concerns.[^208]
Application Submission: The applicant submits a complete permit application package, including all required forms, documents, and supporting materials, to the DSL.
Completeness Review
Public Notice
Agency Review
Permit Decision
Appeal Process
Throughout the review process, the DSL evaluates the project based on its potential impacts to wetlands, waterways, and other aquatic resources, as well as its consistency with the Oregon Removal-Fill Law and other applicable regulations. The agency may also consider the project's purpose, alternatives, and proposed mitigation measures in making its permit decision.
Removal-Fill Permit Public Participation & Stakeholder Engagement
Public participation is an essential component of the Oregon Removal-Fill Permit process, providing an opportunity for interested parties to review and comment on proposed projects that may impact wetlands, waterways, and other aquatic resources in the state.
When a complete permit application is received, the Oregon Department of State Lands (DSL) issues a public notice describing the proposed project, its location, and potential environmental impacts. The notice is typically published in a local newspaper, mailed to adjacent property owners and interested parties, and posted on the DSL website.
The public comment period usually lasts 30 days, during which any person or organization may submit written comments, concerns, or objections regarding the proposed project. Public comments may address issues such as:
- Potential impacts to wetlands, waterways, fish and wildlife habitat, or other environmental resources
- Consistency with local land use plans or zoning regulations
- Adequacy of proposed mitigation measures
- Alternatives that may have less environmental impact
- Other relevant factors
The DSL is required to consider all substantive comments received during the public comment period in its permit review and decision-making process. The agency may request additional informatie
Transect can help: Streamline development workflows
Accelerate decision making and streamline collaboration, without disrupting your current workflows.
Learn MoreTECHNOLOGY SOLUTIONS FOR PERMIT COMPLIANCE
Leveraging Technology for Oregon Removal-Fill Permit Compliance
Technology plays a crucial role in streamlining and enhancing the Oregon Removal-Fill Permit compliance process by providing efficient data management, site assessment, and monitoring tools. By leveraging technology, developers and permit applicants can improve efficiency, accuracy, and transparency throughout the state permit compliance process.
Common tools and platforms used in Oregon for permit compliance include:
- Geographic Information Systems (GIS) for spatial analysis and mapping
- Drones and satellite imagery for remote site assessment and monitoring
- Environmental data management software for organizing and analyzing data
- Online permit application and tracking systems for streamlined submissions and updates
These technologies offer numerous benefits, such as:
Benefit | Description |
---|---|
Increased Efficiency | Automate tasks, reduce manual errors, and save time |
Improved Accuracy | Collect and analyze precise data for informed decision-making |
Enhanced Transparency | Share data and updates seamlessly among stakeholders |
Cost Savings | Reduce costs associated with manual processes and field visits |
By incorporating technology into the Oregon Removal-Fill Permit compliance process, developers and permit applicants can navigate the state's environmental regulations more effectively and efficiently.
Transect: An Innovative Solution for Site Selection & Environmental Due Diligence
Transect is an all-in-one environmental due diligence solution that combines software knowledge with hands-on field experience to revolutionize site selection and permitting for industries such as solar, wind, renewable energy, and more. This innovative platform offers a range of features and benefits tailored to streamline the Oregon Removal-Fill Permit process:
- Swift Site Pinpointing and Suitability Analysis: Quickly determine the best sites for project development within Oregon, considering state-specific environmental factors and regulations.
- Real-time Data Updates and Critical Issues Identification: Stay updated with the latest Oregon environmental data and identify potential issues early in the site selection process.
- Versatility across Multiple Industries and Project Types: Suitable for a wide range of industries, including solar, wind, and other renewable energies, within the state of Oregon.
- User-Friendly Interface and Intuitive Workflow: Ensure ease of use and efficiency in project planning for Oregon-specific requirements.
- Efficiency Gains and Cost Savings: Reduce the costs and delays typically associated with traditional environmental due diligence in Oregon.
- Proactive Risk Mitigation and Compliance Assurance: Proactively address potential compliance issues, minimizing risks related to Oregon Removal-Fill Permit regulations.
Transect's unique capabilities help developers and permit applicants streamline their site selection and permitting processes in Oregon. By leveraging Transect, users can reduce costs and delays associated with traditional environmental due diligence methods while ensuring ongoing compliance with Oregon Removal-Fill Permit requirements. This innovative solution provides a comprehensive approach to navigating the state's environmental regulations, empowering developers to make informed decisions and achieve project success.
POST-PERMIT COMPLIANCE & MANAGEMENT
Removal-Fill Permit Conditions & Compliance Obligations
Oregon Removal-Fill Permits typically include a range of conditions and requirements designed to minimize environmental impacts and ensure compliance with state regulations. These conditions may include:
Impact Minimization Measures: Requirements to implement best management practices (BMPs) to reduce the extent and duration of impacts on protected resources, such as wetlands and waterways.13
Mitigation Commitments: Obligations to compensate for unavoidable impacts through restoration, enhancement, or preservation of similar resources, often at a specified ratio (e.g., 2:1 mitigation ratio for wetland impacts).
Reporting Obligations: Requirements to submit regular reports documenting compliance with permit conditions, including the implementation of impact minimization measures and progress on mitigation commitments.14
Understanding and adhering to these conditions is crucial for maintaining compliance with state regulations. As emphasized in the Oregon Removal-Fill Law:
"A permit is required for any removal, fill, or alteration of more than 50 cubic yards of material within the bed or banks of waters of this state, unless the activity is specifically exempted."15
Adhering to permit conditions not only ensures legal compliance but also promotes sustainability and responsibility in project development within the state. By minimizing environmental impacts and fulfilling mitigation commitments, permit holders demonstrate their commitment to Oregon's conservation goals and contribute to the long-term health of the state's natural resources.
Removal-Fill Permit Monitoring, Reporting & Recordkeeping Requirements
Oregon Removal-Fill Permits typically involve ongoing monitoring, reporting, and recordkeeping requirements to ensure compliance with permit conditions and state regulations. These requirements may include:
Monitoring: Regular site inspections and assessments to track the implementation of impact minimization measures, progress on mitigation commitments, and overall compliance with permit conditions.16
Reporting: Submission of periodic reports (e.g., annual reports) to the Oregon Department of State Lands (DSL), detailing the status of the project, compliance with permit conditions, and any issues or corrective actions taken.
Recordkeeping: Maintaining accurate and complete records of all activities related to the permitted project, including monitoring data, mitigation plans, and correspondence with regulatory agencies. These records must be retained for a specified period, typically a minimum of five years.17
Effective data management practices, such as maintaining organized files and using standardized templates for reports, can help streamline the reporting process and ensure consistency in documentation. As stated in the Oregon Administrative Rules:
"Permittees shall allow Department representatives access to the project site for the purpose of inspecting compliance with the permit."18
Accurate and timely reporting is essential for demonstrating compliance with state permit conditions and maintaining good standing with regulatory agencies. Failure to meet reporting and recordkeeping requirements can result in enforcement actions and jeopardize the validity of the permit.
Enforcement and Penalties for Non-Compliance with Removal-Fill Permit
Non-compliance with Oregon Removal-Fill Permit conditions can result in various enforcement actions and penalties under state law. The Oregon Department of State Lands (DSL) has the authority to issue the following:
Administrative Penalties: Monetary fines for violations of permit conditions or state regulations, with the amount determined based on the severity and duration of the violation.19
Civil Fines: Substantial monetary penalties imposed through civil court proceedings, which can be significantly higher than administrative penalties.20
Criminal Charges: In cases of willful or egregious violations, individuals may face criminal charges, including misdemeanor or felony convictions, and potential imprisonment.21
Permit Revocation: The DSL may revoke a Removal-Fill Permit if the permit holder fails to comply with conditions or commits serious violations, effectively halting the project until the issues are resolved.22
Common violations that can trigger enforcement actions include:
- Conducting removal or fill activities without a valid permit
- Exceeding the authorized scope of work or impact thresholds
- Failing to implement required impact minimization measures or mitigation commitments
- Submitting false or misleading information in permit applications or compliance reports
As stated in the Oregon Removal-Fill Law:
"Any person who violates any provision of ORS 196.800 to 196.900 or any rule, order or permit adopted or issued under ORS 196.800 to 196.900 shall be subject to a civil penalty in an amount to be determined by the director of not more than $10,000 per day of violation."23
To mitigate enforcement risks and ensure ongoing compliance, it is crucial for permit holders to take prompt corrective action when violations are identified and maintain open communication with the DSL. Proactively addressing compliance issues and working collaboratively with the permitting agency can help prevent escalation of enforcement actions and protect the project's legal standing.
ADDITIONAL RESOURCES & UPDATES
Recent Changes & Updates to Oregon Removal-Fill Permit
In recent years, there have been several notable changes and updates to the Oregon Removal-Fill Permit. These changes have altered the scope and requirements of the permit, and stakeholders should be aware of these updates to ensure compliance with the current regulations.
- Senate Bill 1582 (2022) - Effective January 1, 2023^500
- Amended the definition of "waters of this state" to include wetlands and other aquatic resources not previously covered under the permit.
- Expanded the jurisdiction of the Oregon Department of State Lands (DSL) to regulate activities in these additional waters.
- Implications: Projects impacting a wider range of aquatic resources now require a Removal-Fill Permit, increasing the number of projects subject to the permit requirements.
- House Bill 2436 (2021) - Effective June 23, 2021^501
- Introduced a new exemption for certain voluntary stream restoration projects that meet specific criteria.
- Streamlined the permit process for qualifying restoration projects, reducing the administrative burden on project proponents.
- Implications: Encouraged more voluntary stream restoration projects by simplifying the permitting process for these activities.
- DSL Administrative Rule Changes (2020) - Effective January 1, 2021^502
- Updated the permit application requirements, including new information on project alternatives and avoidance and minimization measures.
- Revised the mitigation requirements for unavoidable impacts, emphasizing a watershed-based approach to mitigation planning.
- Implications: Project proponents must provide more detailed information in their permit applications and consider a broader range of mitigation options to offset project impacts.
REFERENCES
Oregon Department of State Lands. (n.d.). Removal-Fill Permit. https://www.oregon.gov/dsl/WW/Pages/Permits.aspx ↩
Oregon Revised Statutes. (2019). ORS 196.795-990. https://www.oregonlegislature.gov/bills_laws/ors/ors196.html ↩
Oregon Administrative Rules. (2019). OAR 141-085. https://secure.sos.state.or.us/oard/displayDivisionRules.action?selectedDivision=412 ↩
Oregon Department of State Lands. (n.d.). Removal-Fill Permit. https://www.oregon.gov/dsl/WW/Pages/Permits.aspx ↩
Oregon Revised Statutes. (2019). ORS 196.800. https://www.oregonlegislature.gov/bills_laws/ors/ors196.html ↩
Oregon Administrative Rules. (2019). OAR 141-085-0515. https://secure.sos.state.or.us/oard/viewSingleRule.action?ruleVrsnRsn=15863 ↩
Oregon Department of State Lands. (n.d.). Removal-Fill Guide. ↩
Oregon Administrative Rules. (2019). 141-085-0515: Exemptions from Permit Requirements. Retrieved from https://secure.sos.state.or.us/oard/viewSingleRule.action?ruleVrsnRsn=24428 ↩
Oregon Department of State Lands. ↩
Oregon Administrative Rules. (2019). 141-085-0515: Exemptions from Permit Requirements. Retrieved from https://secure.sos.state.or.us/oard/viewSingleRule.action?ruleVrsnRsn=24428 ↩
Oregon Department of State Lands. ↩
Oregon Administrative Rules. (2019). 141-085-0515: Exemptions from Permit Requirements. Retrieved from https://secure.sos.state.or.us/oard/viewSingleRule.action?ruleVrsnRsn=24428 ↩
Oregon Administrative Rules, OAR 141-085-0565 - Permit Conditions. ↩
Oregon Administrative Rules, OAR 141-085-0615 - Monitoring and Reporting Requirements. ↩
Oregon Revised Statutes, ORS 196.810 - Prohibition against removal from bed or banks of waters; exceptions. ↩
Oregon Administrative Rules, OAR 141-085-0615 - Monitoring and Reporting Requirements. ↩
Oregon Administrative Rules, OAR 141-085-0565 - Permit Conditions. ↩
Oregon Administrative Rules, OAR 141-085-0550 - Inspections. ↩
Oregon Revised Statutes, ORS 196.890 - Civil Penalties. ↩
Oregon Revised Statutes, ORS 196.890 - Civil Penalties. ↩
Oregon Revised Statutes, ORS 196.895 - Imposition of Civil Penalties. ↩
Oregon Administrative Rules, OAR 141-085-0575 - Permit Revocation. ↩
Oregon Revised Statutes, ORS 196.890 - Civil Penalties. ↩
Transect can help: Pinpoint environmental risks early
Reduce unforeseen delays and costs by identifying environmental risks early-on using unmatched data.
Learn MoreA Note to Our Readers: We hope this guide is a valuable resource in helping you better understand the Removal-Fill Permit. However, it's not a substitute for professional advice and doesn't cover every scenario. Always consult with regulatory bodies and professionals for the most current advice and project-specific guidance.